Selected Work · 2024
Solar facade for sports infrastructure
Munich, Germany48.1351° N · 11.5820° E
187 kWp integrated facade · IEC 61215 + EN 50583 certified · 9-month deployment.

The challenge
Problem
A municipal sports complex needed to meet Bavaria's renewable energy mandate without compromising the architect's vision for a unified, monolithic facade. Conventional rooftop PV was ruled out due to limited roof area and shading from neighbouring structures.
Our role
Solution
Stillpage led technology selection across five candidate suppliers, ran independent shading and yield modelling, and coordinated certification with TÜV. We oversaw installer training and on-site commissioning, delivering a fully integrated south- and west-facing facade in 9 months from contract signing.
By the numbers
Technical specifications
- Installed capacity
- 187 kWp
- Facade area
- 1,420 m²
- Annual yield
- 168 MWh
- Specific yield
- 898 kWh/kWp
- CO₂ offset / year
- 76 t
- Deployment time
- 9 months
Compliance
Certifications
- IEC 61215 (crystalline silicon performance)
- EN 50583 (BIPV product + system)
- DIN 4102-1 (fire classification B1)
- Bavaria municipal building permit
Technology
BIPV types deployed
- Opaque crystalline silicon facade modules
- Custom-printed ceramic frit cover glass
- Ventilated rear-mounted rail system